Project Jupiter Reaches Energization Milestone of Being Someone Else's Problem
The 2.45 GW campus hasn't energized yet, but its construction debt already moves faster than any electron in Doña Ana County.

Written Wednesday morning, Nov 18, in America/New_York. The HSBC sale was first reported by Bloomberg on Monday evening, citing people familiar with a private trade. The September force majeure notice is also treated as a report. On-the-record comments are labeled. Satire. Not investment advice.
Project Jupiter is a 1,400-acre data center campus in Santa Teresa, New Mexico, designed for 2.45 gigawatts, built by STACK Infrastructure for Oracle as part of the Stargate build-out. The first hall was topped out in late October. The air permit for its power plant is still pending. The gas pipeline that would feed its microgrid is not in service. No electron has left the site.
A loan has. On Monday evening Bloomberg reported that HSBC sold about $300 million of the project's construction debt at prices in the mid-80s, a slice of an $18 billion package arranged in late 2025 by about 20 banks. The sale cleared below the 89 to 91 cents the syndicate was quoting in September.
This gives us the metric. Time-to-power is the interval before the first electron. Time-to-exit is the interval before the first lender wants out. In Doña Ana County, time-to-exit got there first.
Time-to-power, meet time-to-exit
STACK Infrastructure, a unit of Blue Owl Capital, is building Jupiter for Oracle, part of the campus announced with OpenAI and SoftBank. The sale took place several weeks before it was reported, shortly after Oracle sent the developer a force majeure notice, according to people familiar with the matter cited by Bloomberg. HSBC declined to comment. Oracle did not have an immediate comment. The buyer was not named.
Mid-80s is a price, not a disclosed accounting loss. Upfront fees and carrying value were not published, so this desk is not inventing a hole in anyone's income statement. It is still the cleanest print the loan has received, and it cleared below September's range.
That post has about 34,000 views and does the arithmetic at 85 cents, arriving at $255 million. Mid-80s is what Bloomberg reported; 85 is an interpolation. The loan found a buyer. The campus has not found a hearing date.
The notice, as reported
Bloomberg first reported the force majeure notice on Sept 24, and CNBC confirmed Oracle had sent it to the developer. The notice, per people familiar with the matter, would let Oracle delay payments if the campus does not come online in 2028 as planned. It did not say Oracle was trying to leave as tenant. Oracle declined the funeral:
"Project Jupiter remains on our planned schedule. We are fully committed to New Mexico and confident in our path forward."
Blue Owl added: "This notice does not change the financial commitments to this multi-year project." This desk has not seen the notice. The force majeure claim is a report; the company statements are on the record. A later write-up, citing Bloomberg, said a recognized power-related event could delay rent by as much as three years once payments begin. That mechanism has not been confirmed in a filing this desk has read, and is marked as reported.
The press release got out first
The campus has been announced as a generational project, which is the standard unit of measurement in this sector. Doña Ana County authorized industrial revenue bonds with a ceiling of $165 billion over 30 years. That figure is a tax-abatement structure, not the loan and not money the county borrowed. The construction loan is $18 billion.
The community benefits agreement promised to "power itself with an onsite microgrid," and that the microgrid "will not impact existing customers' power reliability or costs." Then, on Oct 13, Oracle proposed an energy service agreement with El Paso Electric for construction, commissioning, and backup power: at least $100 million over 10 years, plus up to $55 million a year in credits for New Mexico ratepayers. The primary source, Oracle said, "will continue to be" the Bloom Energy fuel cell microgrid. There was "no change to our plan." An Oracle executive helpfully timestamped it: the company was acting "well before our data center comes online."
Two days later, Oracle and the microgrid developer proposed a permit refinement cutting permitted emissions by about 35 percent, via an enforceable operating cap of 1,600 megawatts, about 65 percent of the 2.45 gigawatt design. Planned IT capacity, Oracle said, is unchanged. Redundancy, in this structure, is both a reliability feature and a way to lower the permitted number. On Oct 22, the builders placed the final beam on the first hall. The building has a roof. The debt market is less interested in the beam.
The permits did not get the memo
On Oct 27, the Doña Ana County Commission voted 5-0 to authorize notice of a potential breach of the bond agreements over the power plan. The vote does not establish a breach or cancel the bonds; the county's objection is that a utility hookup sits uneasily next to a written promise to power the campus on site. The dispute is unresolved.
The power plant still needs an air quality permit from the New Mexico Environment Department, with a public hearing kept for Dec 7 after a revised application. As of this morning, this desk has not seen a final permit. The gas is on its own clock: Energy Transfer's Green Chile pipeline, the lateral meant to feed the microgrid, had its in-service date moved to February 2027 per FERC filings, after the State Land Office rejected rights-of-way for parts of the original route. FERC has issued an environmental assessment, not a final certificate.
The buildings can rise without a permit to run 2.45 gigawatts of fuel cells. The fuel cells cannot. Time-to-power, in Doña Ana County, is still a queue.
The syndicate looks for the door
The $18 billion financing is split into tranches tied to individual buildings, with SMBC, BNP Paribas, Goldman Sachs and MUFG named as administrative agents in contemporaneous reporting. Banks that hold this kind of paper usually keep it, and a lender leaving before completion often takes a discount larger than the upfront fees. The exit is optional. The price is not.
HSBC is not the only name in the doorway. Bloomberg reported that ING is auctioning about $500 million of data center loans in a bids-wanted process due Nov 19, including a $25 million piece of the New Mexico Stargate project. ING declined to comment. Separately, reports citing the FT said Societe Generale was seeking buyers for about $300 million of debt tied to other Oracle campuses in Wisconsin and Texas, at indications above 90 cents. Those are not Jupiter loans, and this desk has not seen a confirmed sale. The pattern is the point. The press release describes a campus. The secondary market describes an exit.
What the equity tape did
Oracle closed Tuesday, Nov 17, at $115.00, down 3.43 percent, the first regular session after Bloomberg's Monday-evening report. The stock had already fallen 5.0 percent on Monday, before the story reached the tape, so this desk is not assigning Monday to it. The five-year credit default swap was at 292 basis points on Nov 2, up 265 percent in a year per CNBC, after S&P cut Oracle to BBB- in July, one notch above junk. This desk could not find a confirmed CDS print for this week's sale, and will not invent one.
What the press release said vs what the debt market said
| Item | The press release | The debt market |
|---|---|---|
| Size | Up to $165B of industrial revenue bonds over 30 years | An $18B construction loan, ~$300M of it changed hands |
| Power | 2.45 GW on-site microgrid, no impact on ratepayers | Air permit pending; pipeline target Feb 2027; utility backup now disputed by the county |
| Schedule | "Remains on our planned schedule" | A reported force majeure notice aimed at payment timing if 2028 slips |
| Capacity | Planned IT capacity "unchanged" | A proposed 1,600 MW cap, ~65% of design |
| Status | "Well before our data center comes online" | Mid-80s on the loan, below September's 89-91 |
| Energization | A beam on the roof | A loan that has already left |
The campus has a topping-out ceremony and a loan that already found a buyer at a discount. In the credit market, that is an energization. See also Oracle's other milestone, where it used a four-year fundraising allowance in five days.
The electrons are still waiting for a hearing date.
Sources
- HSBC sale (Bloomberg, via Investing.com): investing.com/news/stock-market-news/hsbc-…
- Force majeure (CNBC): cnbc.com/2026/09/24/oracle-data-center-for…
- El Paso Electric ESA (Oracle): oracle.com/news/announcement/oracle-propos…
- Loan-price arithmetic post: x.com/wallstengine/status/2122654383502450…
- County vote, air-permit hearing, Green Chile pipeline, CDS and S&P: Albuquerque Journal, Source New Mexico, CNBC.
- Satire. Not investment advice. Reports are labeled as reports; on-the-record statements are labeled as such. The publisher is long IREN and CIFR, holds no Oracle and none of the Project Miner loan, which this desk notes so you know it is not quietly in the doorway too.