Applied Digital Booked $5.4 Billion for 150 Megawatts Due in 2028, Subject to the Utility

An unnamed investment-grade hyperscaler signed an 18-year lease worth $5.4 billion in base rent, or $12.7 billion over 33 years with renewals, pushing Applied Digital's headline backlog above $41 billion and $100 billion with renewals. The power is due in 2028, pending the utility.

By Priya Vanterpool · Neocloud Desk · November 23, 2026Share on X
MS Paint illustration of Applied Digital's four escalating revenue figures ($5.4B, $12.7B, $41B+, ~$100B) with unnamed tenant and campus fields stamped Due 1H 2028 Pending Utility, alongside its separate 7:45 AM 364-day $300M bridge loan and +22.11 percent session move.

Applied Digital just reminded Wall Street that one press release can print four different numbers in the billions before a single electron leaves the substation.

At 8:00 AM ET on Monday, Applied Digital announced an 18-year lease for 150 megawatts of critical IT capacity with a tier-one investment-grade hyperscaler it declined to name, at a campus it also declined to name. Depending on which sentence you stop reading on, the release puts $5.4 billion in base-term contracted revenue on the board, $12.7 billion if every renewal option is exercised across 33 years, more than $41 billion in total company base-term backlog, or roughly $100 billion if every renewal across the whole portfolio gets exercised.

On simple derived arithmetic from the company's own figures, the new lease averages $2.0 million per megawatt per year ($5.4 billion across 18 years and 150 MW), roughly 21 percent higher than the derived $1.65 million per megawatt per year average on its June 8 Delta Forge 2 lease ($5.2 billion across 15 years and 210 MW). That is strictly headline arithmetic before construction costs, escalators, or operating expenses, and Applied Digital said only that the new deal carried improved commercial terms and higher pricing. As we track in our Neocloud Field Guide (full deep-dive teardown coming soon), powered-shell landlords like Applied Digital live and die on two things: tenant credit quality (now roughly 75 percent investment-grade on base revenue) and actually energizing the building on time.

On that second point, the release is refreshingly blunt. Delivery of the 150 MW is "currently anticipated to begin in the first half of calendar 2028, subject to applicable development milestones, utility arrangements and regulatory approvals." Project financing for Delta Forge 1, Polaris Forge 3, and Delta Forge 2 is targeted for the first half of 2027, alongside the company's $5 billion programmatic equity partnership with Macquarie Asset Management.

Same-Morning Release (Nov 23)Clock / StructureHeadline FiguresKey Condition
7:45 AM ET: Delta Forge 1 Bridge364-day delayed-draw loan$300M at SOFR + 300 bpsDraws require state electrical-rate approval
8:00 AM ET: New 150 MW Lease18-year base (33-yr w/ renewals)$5.4B base / $12.7B w/ renewalsDelivery 1H 2028, pending utility & permits
Total Portfolio Backlog>1.6 GW contracted IT load>$41B base / ~$100B w/ renewals~75% investment-grade base revenue
APLD Tape (CNBC, 1:20 PM ET)Session move vs. $11.49 Fri close$14.03 (+22.11%, $4.24B cap)Set 52-week low of $11.31 on Nov 20

Fifteen minutes before the lease release, at 7:45 AM ET, Applied Digital dropped a separate financing announcement for its Louisiana campus, Delta Forge 1: a $300 million senior secured delayed-draw bridge loan from an unnamed global financial institution priced at SOFR plus 300 basis points with a 364-day maturity. Draws require construction milestones and state commission approval of electrical rates, and the company noted it expects to seek additional financing to finish that campus. The two releases cover separate corporate milestones, yet sitting side by side they capture the entire Guppy Index trade in miniature: leases measured in decades, bridge loans measured in 364 days.

By 1:20 PM ET, CNBC and Yahoo Finance both printed APLD at $14.03, up 22.11 percent from Friday's $11.49 close (just pennies above Friday's $11.31 52-week low). Every megawatt will be monetized, preferably across 33 years of renewal math before the utility signs off on the 2028 plug.

Sources

Desk Wire · Reader Notes

Comments (0)

Mock the filings, not private individuals

Loading reader notes...

The newsletter

Liked that? Get the next one free.

No paywall, no spam. Enter your email and the weekly Every Megawatt lands when our free tokens refresh.

More research